Balfour Beatty Management
The range of activities Balfour Beatty Management has carried out on this project has been vast, ranging from concept design of HV protection systems, substation, earthing, HV and LV cabling design.  The procurement of switchgear, transformers and control systems, the management, planning and supervision of contractors through to the commissioning and energisation of the networks.

The 4-year Channel Tunnel Rail Link Design Project

Value: 

£45million

Timescale:

4 years.

Background:

Section 2 of the Channel Tunnel Rail Link (CTRL) now renamed High Speed 1 runs 39km from Southfleet Junction in Kent to the magnificent refurbished station at St Pancras, London and is the first new railway in Britain for 100 years.

The route has 17km of duel tunnels, in three sections, under the Thames, from Dagenham to Stratford and then from Stratford to just short of St Pancras.  Additional to the main route, from Stratford there is a 1 km tunnel connection to the new Eurostar maintenance depot at Temple Mills.

Our Brief:

Balfour Beatty Management won the £45m contract to supply twenty seven 11kV/400V substations located at various positions along the Section 2 route after competing the installation of 4 smaller substations on Section 1. 

Services Provided:

The project consisted of five 11kV Networks at Ebbsfleet, Rainham, London Tunnel (the tunnels from St Pancras to Dagenham), Temple Mills and St Pancras Station.  The combined capacity of the order of 33MVA, with individual networks having capacity ranging from 750kVA at Rainham up to 8MVA on the London Tunnel.  We installed over 180 circuit breakers, 60 11kV/11kV and 11kV/400V transformers and over 270 LV circuit breakers.

Our Achievements:

The specification held many challenges, not least the design and supervision of the installation of 60km of 11kV cabling which had to have a design life of 40 years.  The system had to be earthed in a manor that had to be safe to the public and
future proofed against increases in fault levels due to infrastructure upgrades.
We also had to interface with numerous other contractors on the project in which we did not have contractual links.  Once into the project additional challenges were
encountered at the St Pancras Station, where there were space constraints and the demanding requirements of working in an English Heritage building. 

While these issues where of close concern to the team, we were foremost aware of
the importance of the safety aspects required on a railway such as CTRL.

As the 11kV cabling had to run in parallel with the track, the design of the cable had to be substantial enough to allow traction currents to pass down the screens without reducing the rating.

To achieve this with the HV cabling we paid special care with the terminations, using outdoor terminations on the internal cable boxes and additional cable box heaters to ensure that moisture could not cause breakdown. Experienced cable jointers were provided with additional training prior to making the cable joints. Each joint was checked during and after installation by a team of independent inspectors. Each cable was tested using the latest techniques. Firstly over-sheath tests to prove the outer integrity of the cable and thus ensure moisture could not enter, the cables where then partial discharge mapped to ensure reliability over the design life.

To make sure that traction currents could not enter the electricity supplier’s networks, 11kV/11kV isolation transformers have been employed. This isolation transformer mitigated the potential of direct currents causing corrosion in remote locations however it created problems with the earthing of the substations. The isolation transformer creates a break in the cable screen therefore all earth fault current would have to pass through the mass of earth, thus giving a potential hazard of high touch and step voltages. As very low earth resistance values from large earth mats were not possible, a device that bridges the two earth systems was developed to solidly bond the systems under the unlikely event of a fault, but to isolate the two systems under normal operations.

The greatest challenge for our team over the last four years was the effort required in the design, installation and energisation of our three 11kV Substations at St Pancras.
Working within the confines of an English Heritage grade1 listed building; Balfour Beatty Management had to ensure its design was constructible, safe and maintainable without disturbing or damaging the fabric of the building.

Energisation of the five 11kV networks has required the setting up of a control room staffed by control and deputy engineers and a team of ten senior authorised personnel. By using a system of procedures, safety rules, network control mimics and a web based substation-monitoring system, the team of SAP’s have ensured the safe 11kV and 400V energisation in an environment containing dozens of different contractors over a wide geographical area.

The range of activities Balfour Beatty Management has carried out on this project has been vast, ranging from concept design of HV protection systems, substation, earthing, HV and LV cabling design.  The procurement of switchgear, transformers and control systems, the management, planning and supervision of contractors through to the commissioning and energisation of the networks. The project has been an outstanding success thanks to the co-operation of the design, construction, subcontractor and client teams working together on a project that probably will not be repeated for many years to come.

 

In the long term, we all have to do something different. We must challenge our current working practices, our ownership of health and safety and how each one of us can contribute towards making what we do safer - Zero Harm

© Balfour Beatty plc is registered in England as a public limited company; Registered No: 395826; Registered Office: 130 Wilton Road, London, SW1V 1LQ