Earls Court Station PPP Modernisation Project - Balfour Beatty Management
This project utilises a variety of our services, including project management (design, approvals and construction); commercial, procurement and requirements management.

Earl's Court Station PPP Modernisation Project

Value:

The project is worth approximately £28m

Timescales:

January 2005 saw the scoping and outlining design by a previous (non-Balfour Beatty Management) team. We became involved one year later and took over management of the project in full in March 2006. The protection deck over the platforms and the ticket hall was installed between December 2006 and July 2007, in parallel with the temporary lighting installation. The full permanent design was issued in September 2007, with the completion of a detailed inspection of the existing structure. The temporary roof installation over the train shed roof commenced in November 2007, and the train shed roof refurbishment was carried out from January to October 2008. Then the permanent lighting was installed in parallel with the protection deck removal, with completion in April 2008.

Background:

This project was born out of the Metronet PPP contract with London Underground (LU).

Our brief:

The provision of a first-class project management team to deliver this project for Metronet.

Services provided:

This project utilises a variety of our services, including project management (design, approvals and construction); commercial and procurement management; and requirements management.

Our achievements:

Balfour Beatty Management managed the design and approvals, including prioritising the protection deck to allow an early start on site. This included working closely with Metronet and LU to understand their detailed scope, technical requirements and concerns, to gain the required technical and commercial approvals. Planning consent was also gained for these works to the Grade II listed structure.

To minimise the effect on the passengers and operational railway a 3,000m2 protection deck was installed, with moveable temporary roofs to provide protection from the weather. Up to ten coats of paint were removed from the wrought iron structure, using a chemical gel, and long life paint applied. The existing cladding and Georgian wired glazing were replaced with low maintenance aluminium Kalzip cladding which is similar to the original in appearance, and toughened, laminated and self cleaning glazing. A maintenance gantry and eaves walkways have been installed, and together with the low maintenance materials use for cladding and glazing, this will reduce whole life costs.

Balfour Beatty Management have established a strong project team and built close working relationships with both Metronet and the London Underground. These strong bonds have meant the opportunity to offer our people a great deal of development opportunities, working on multi-disciplinary, multi-life cycle projects with further opportunities in project and contract management. Opportunities with such immense scope are rare in our industry.

 

The Earls’s Court project has produced a superbly refurbished heritage roof, on time and significantly below budget

 

Mike Quinn - Metronet

© Balfour Beatty plc is registered in England as a public limited company; Registered No: 395826; Registered Office: 130 Wilton Road, London, SW1V 1LQ